On Tue, Jul 11, 2006 at 11:41:21AM -0400, Sean Hennessey wrote:
> We have situation where we are collecting a lot of rrd data for a specific
> test case (will be 16 data points). We'd like the ability to create two
> different graphs off of one rrd file (and one column on the hobbit page). We
> have a test called gt3_data that gets fed data from a script on a remote box
> via the bb command. This scripts sends up 8 different data values to be
> stored in the the gt3_data rrd. Currently we are graphing all the data
> points on one graph, but it is really ugly. We'd like to split it into two
> graphs, but we can't seem to find a way to tell hobbit to make two graphs
> based off of one column from the webpage. It doesn't make sense in our case
> to split the test into two different tests, but it does make sense to split
> the data into two graphs. Does anyone know if what this is possible?

No, it's not possible with the current code.

It ought to be, I agree. But the whole handling of which graphs go where 
needs some major work; the current setup was adopted from Big
Brother/LARRD and is not very flexible.