On Tue, Jul 11, 2006 at 11:41:21AM -0400, Sean Hennessey wrote:
We have situation where we are collecting a lot of rrd data for a specific
test case (will be 16 data points). We'd like the ability to create two
different graphs off of one rrd file (and one column on the hobbit page). We
have a test called gt3_data that gets fed data from a script on a remote box
via the bb command. This scripts sends up 8 different data values to be
stored in the the gt3_data rrd. Currently we are graphing all the data
points on one graph, but it is really ugly. We'd like to split it into two
graphs, but we can't seem to find a way to tell hobbit to make two graphs
based off of one column from the webpage. It doesn't make sense in our case
to split the test into two different tests, but it does make sense to split
the data into two graphs. Does anyone know if what this is possible?
No, it's not possible with the current code.
It ought to be, I agree. But the whole handling of which graphs go where
needs some major work; the current setup was adopted from Big
Brother/LARRD and is not very flexible.